Dendro and Pfaff final delivery to SL Saltsjöbanan

In November, the first lift with C10 vehicles was made in the newly built workshop in Neglinge on Saltsjöbanan and the equipment was handed over to the client.

(more…)

Dendro and Pfaff deliver bogie lifts to SL Saltsjöbanan

In conjunction with the delivery of the new vehicle lifts, a new 16 tonne bogie lift and specially adapted jack stands were also delivered to replace the bogie.

Roof platforms in Eskilstuna handed over

Now have the total 648 meter moving roof platforms in Eskilstuandepån been tested with MÄLAB’s new ER 1 Stadler DOSTO trains. It is now possible to perform safe and secure work on the roofs of the vehicles.

Dendro Lift delivers 50-ton jack stands

Dendro, together with Bengtsson Maskin, has delivered a lifting solution with Dendro PB50 jack stands to Cementa in Slite for servicing the 100-ton dumper Caterpillar 77D